2013-Oct-5 - Wooroloo - Steelworks #97
After work on Friday I shot out to site and drilled another 7 x 12 mm holes in the PFC.

Again I did not get to bed until 1.00 am.

The next morning I slept right in until 8.30 am and started work on the purlins at 9.00 am

Not a lot to report really.

I retrieved all the purlins out of storage, washed down two of them, installed 2 that were prepared, prepared another 5, installed them.

All up 14 purlins are now installed on the back veranda.


Purlins installed by the end of the day